| 1.0 |
Permits & Clearance |
Underground Utility Survey (GPR), Trial Pits & NOC from Utilities |
H
H
W
|
Project HSE Plan / Municipal Bylaws |
100% utility clearances received; trial trenches dug by hand excavation near existing live gas/water/cables |
Surveyor & Safety Manager |
| 2.0 |
Excavation |
Bulk Earthwork Excavation, Sloping / Benching & Spoil Heap Management |
W
W
S
|
OSHA 1926 Subpart P / ACI |
Excavated slopes benched at certified angles; spoil heaps setback >= 1.5m from trench crest |
Earthworks Superintendent & QC |
| 3.0 |
Shoring & Safety |
Trench Shoring Box, Soldier Piles, or Sheet Piling Installation |
H
H
W
|
BS 8004 / CIRIA Report C760 |
Engineered shoring installed for all excavations deeper than 1.2m; access ladders placed every 7.5m |
Structural QC & HSE Inspector |
| 4.0 |
Dewatering |
Wellpoint Dewatering System Operation & Groundwater Monitoring |
W
W
S
|
Project Technical Specs |
Water table maintained at least 500mm below bottom of formation level; discharge silt traps operating |
Dewatering Specialist & QC |
| 5.0 |
Subgrade Acceptance |
Formation Level Proof Rolling & Plate Load / In-Situ Density Testing |
H
H
W
|
ASTM D1194 / ASTM D1557 |
Formation depth matches IFC drawings; subgrade compacted to >= 95% MDD; zero soft pockets |
Geotechnical Engineer & Consultant |
| 6.0 |
Material Quality |
Backfill Material Classification (A-1-a / Selected Granular Fill) |
H
W
R
|
AASHTO M145 / ASTM D2487 |
Plasticity index <= 6; organic matter <= 1%; gravel/sand grading curves meet approved submittal |
Materials QC & Third-Party Lab |
| 7.0 |
Backfilling Execution |
Layered Backfill Spreading (Max 200mm Loose Lift) & Moisture Conditioning |
W
W
S
|
ASTM D1557 |
Moisture content controlled within +/- 2% of Optimum Moisture Content (OMC); uniform lift thickness |
Earthworks Foreman & QC |
| 8.0 |
Compaction Testing |
Field Density Testing (Nuclear Gauge / Sand Cone Method) |
H
H
W
|
ASTM D6938 / ASTM D1556 |
Compaction >= 95% Modified Proctor density under slabs/roads; 1 test per 250m² per compacted layer |
Independent Testing Lab & Consultant |