Civil Quality Inspection Checklist Hold & Witness Included PDF / Word / Excel

Formwork & Shuttering Inspection Checklist Template

A Formwork & Shuttering Inspection Checklist provides civil QA/QC inspectors and temporary works coordinators with a systematic methodology to inspect formwork assemblies before placing concrete. It verifies dimensional accuracy, plumb tolerances, tie-rod cone waterstops, release agent application uniformity, chambered corners, and Falsework shoring load capacity. Rigorous formwork inspection prevents catastrophic blowouts, concrete bulging, grout leakage, and out-of-tolerance structural elements.

Generate or Tailor this Quality Inspection Checklist in 60 Seconds Catalyst formulation engine automatically embeds your project name, client specs, and standards into Word, Excel, or PDF.
Customize this with Catalyst

Audit-Ready Inspection Matrix & Intervention Points

Standard civil/MEP inspection stages with contractor, consultant, and client intervention codes. Free to reference or export:

Item Stage Inspection Activity / Checkpoint Roles (C / E / O) Reference Standard Acceptance Criteria & Tolerances Responsibility
1.1 Material Verification Shutter Plywood Grade, Film Thickness & Steel Soldiers Check
W R R
ACI 347 / BS 5975 Marine ply 18mm with intact phenolic film; steel walers free of permanent bending or weld fatigue Civil QC Inspector
1.2 Setting Out Kicker Line, Centerlines & Internal Dimensions Verification
H W S
IFC Drawings & ACI 117 Internal clear dimensions within +/- 3mm of structural design drawings Chief Surveyor & QC Inspector
2.1 Assembly Verticality, Plumbness & Alignment of Wall and Column Forms
H H W
ACI 117 Table 4.1 Plumb tolerance <= 6mm per 3m height; total accumulated deviation <= 12mm over building height Civil Site Engineer & Consultant
2.2 Assembly Tie-Rod System, Sleeves, Cones & Waterstop Rings for Retaining Walls
H H W
Project Technical Specs High-tensile tie rods torqued evenly; cast-in waterstop tie-plugs installed on external water-retaining walls Civil Foreman & QC Inspector
2.3 Falsework & Shoring Shoring Tower Bracing, Jack Extensions & Base Plate Bearings
H H W
BS 5975 / Approved Falsework Design Screw jacks extended <= 300mm maximum; diagonal bracing 100% pinned; sole plates seated on firm soil Temporary Works Engineer & QC
2.4 Joints & Gaskets Form Joint Sealing, Foam Gaskets & Foam Tape for Zero Slurry Leakage
W W S
ACI 347 Section 3.2 All plywood joints sealed with compressed neoprene foam tape; zero visible gaps at form junctions Civil Foreman & QC Inspector
2.5 Chemicals Form Release Agent Application Uniformity & Surface Dryness
W W S
ACI 301 Section 4 Non-staining approved release oil sprayed evenly with no puddles, drips, or transfer onto steel rebar Site QC Inspector
2.6 Final Verification Clean-Out Ports Inspection, Debris Flushing & Final Sign-Off
H H W
ACI 301 Bottom clean-out access windows inspected, debris flushed with pressurized air/water, windows bolted shut Civil QA/QC & Consultant RE
Role Key: H Hold Point: Mandatory sign-off required W Witness Point: Formal notification (inspect if present) R Review: Certificate / Submittal check S Surveillance: Continuous audit check

Applicable Standards & Codes

  • ACI 347: Guide to Formwork for Concrete
  • BS 5975: Code of Practice for Temporary Works Procedures and Falsework
  • ACI 117: Standard Tolerances for Concrete Construction and Materials
  • DIN 18202: Tolerances in Building Construction
  • OSHA 1926 Subpart Q: Concrete and Masonry Construction

Common Site QA/QC Mistakes

  • Over-extending screw jacks beyond certified engineering calculations, compromising Falsework stability.
  • Spraying release agent after rebar has been installed, coating reinforcement bars in oil and destroying concrete bond strength.
  • Failing to install clean-out doors at the bottom of tall columns and walls, leaving tie-wire cuttings and debris trapped at the base.
  • Neglecting foam sealing tape along formwork joints, leading to grout leakage, honeycomb voids, and jagged fins.
  • Stripping vertical wall formwork early before concrete attains required self-supporting compressive strength.

Technical Frequently Asked Questions

When can side forms (walls and columns) be safely stripped?
Under ACI 347 and BS 5975, vertical forms for walls, columns, and beam sides can typically be stripped after 24 to 48 hours provided the concrete temperature has stayed above 10°C and concrete has attained sufficient strength to resist surface damage.
What is the allowable plumb tolerance for structural formwork?
According to ACI 117, the maximum allowable deviation from plumb for columns, piers, and walls is 6mm (1/4 inch) in any 3 meters (10 feet) of height, with a maximum cumulative deviation of 25mm across the structure.
How do you prevent water leakage through tie-rod holes in retaining walls?
For water-retaining and basement walls, use tie rods with cast-in central waterstop disks, or install heavy-duty PVC sleeves with elastomeric sealing plugs and non-shrink waterproof crystalline grout post-stripping.